Venice Beach's Sand Is Back. The Jetty Next To It Isn't Even Funded Yet.

September 17, 2026

Venice Beach's Sand Is Back. The Jetty Next To It Isn't Even Funded Yet.

Walk the beach access path north of the Venice Fishing Pier this month and the sand under your feet is different than it was in June. It's wider, for one thing, in some stretches by as much as 100 feet. Keep walking south toward Brohard Paw Park, though, and you'll hit a barricade. Same beach, same week, two completely different stories.

That contradiction is the whole point of this post. Most people who live near this stretch of Gulf Coast have folded these into one mental file labeled "the beach project," as if it's a single thing that's almost done. It isn't. Venice is running two unrelated repairs on two unrelated clocks, and knowing which is which tells you what you can actually expect walking this beach for the rest of the year.

Two Projects, One Stretch of Coastline

The first project is the beach renourishment that's been underway since late May 2026, a $27.5 million effort led by the U.S. Army Corps of Engineers to rebuild 3.2 miles of shoreline from south of the Venice Inlet to south of the Venice Fishing Pier. It's funded entirely by the federal government through the Flood Control and Coastal Emergencies program, an unusual arrangement triggered because Hurricanes Helene and Milton tore up the coastline so badly in 2024 that this cycle qualified as hurricane recovery rather than routine maintenance. That's why it has a firm finish line.

The second is the South Jetty at Humphris Park, a rock-armored structure built in the late 1930s that Hurricane Idalia badly damaged in August 2023. It closed for nearly a year, reopened briefly in July 2024 after emergency rock repairs, and remains a structure without a reconstruction budget or a construction date. It isn't part of the renourishment project. It never was. It just happens to sit close enough to the same shoreline that residents keep asking city staff why one got fixed and the other didn't.

Those are fair questions. The answers, it turns out, come down to two very different funding paths, not two stages of the same repair.

What Actually Finished This Summer

By late August, the heavy lifting on the renourishment was done. Crews had placed nearly 600,000 cubic yards of sand along the full 3.2-mile stretch, dredged from a borrow site roughly 11 nautical miles off the coast of Englewood, and the shoreline had widened by 50 to 100 feet depending on the segment. Sand placement wrapped in Segment 5 near Golden Beach in early August, and the remaining work shifted to cleanup: pulling out equipment, clearing rock, and extending stormwater outfall pipes so drainage keeps working through the wet season.

Steven Berens, the city's stormwater engineering manager, put it plainly in a late August update on the project's progress: the work is nearing the end and coming together well, and public reaction has been positive. Part of that reaction traces back to what this project protected along the way. More than 500 sea turtle nests had to be relocated by Mote Marine Laboratory during construction, a number that reportedly exceeded what Mote's own team was expecting going into the season.

Sharky's on the Pier owner Justin Pachota, whose restaurant sits at the base of the Venice Fishing Pier, has watched the erosion up close for years. He's described the gradual loss of shoreline through repeated storms as something locals could see happening in real time, which makes the wider beach this fall a visible, tangible change rather than an abstract engineering win.

Worth remembering: this isn't the pier's first comeback story this decade. The Venice Fishing Pier itself reopened in September 2025 after its own multi-year hurricane rebuild, with Tampa Bay Marine replacing the decking in Cumaru and Ipe hardwood. That project is finished and separate from the sand now filling in around it.

The One Spot Still Barricaded, and Why That's Different

If you tried to walk your dog at Brohard Paw Park in late August and found the beach access blocked, that wasn't a leftover from the jetty saga. Sarasota County temporarily closed that access point specifically because renourishment crews needed the space to finish placing rock and burying pipe in that section. Officials said at the time the closure would likely last only a matter of days. If you're reading this in September, there's a good chance that gate has already reopened.

That's the kind of detail that matters if you're deciding whether to drive over this weekend versus next month. The Brohard closure is tied to a project with a defined scope and an expected September finish. It is not evidence that anything is behind schedule or unresolved.

A Different Clock: The South Jetty at Humphris Park

The South Jetty tells a slower story. After Idalia's 2023 damage forced a near year-long closure, the Corps of Engineers made emergency rock repairs that let the walkway reopen in July 2024. Since then, the structure has needed further attention, and unlike the beach renourishment, there's no comprehensive repair budget in place yet.

Both the North Jetty, which falls under Sarasota County, and the South Jetty, which is the city's responsibility, are waiting on a congressional appropriation before full reconstruction can even be scheduled. The Corps is expected to release a major maintenance report on the jetty in November 2026, detailing projected costs and a possible construction timeline. Until that report lands, there's no funded project to point to and no construction date to circle on a calendar.

That's a meaningfully longer runway than the beach sand in front of it, and it's worth sitting with why.

Why the Beach Got Fixed First

City officials have heard this question directly from residents: why did the sand get rebuilt before the jetty? The answer isn't about priorities. It's about which bureaucratic clock each project runs on. The beach renourishment stems from a long-standing agreement between the City of Venice and the Army Corps of Engineers dating back to the 1990s, one that requires this kind of maintenance on a planned, recurring cycle. That agreement was already in motion, already funded through the FCCE program because of the hurricane damage, and already had a contractor under contract.

The jetty has no equivalent standing arrangement. Its repair depends on a fresh congressional appropriation, a process that starts from zero every time and has no guaranteed calendar. One project was already on rails when the hurricanes hit. The other is still waiting for the tracks to get built.

What This Means If You Walk This Beach This Fall

If your routine includes this stretch of coastline, here's the practical read. The wider sand from Venice Inlet down toward Brohard Paw Park is the finished product of a decade-plus wait, last renourished in 2015 and delayed further by the 2024 storms before this cycle even began. Expect the last cleanup work, including equipment removal and outfall extensions, to close out through September. The Brohard access point should follow shortly after the rock and pipe work there wraps.

The South Jetty at Humphris Park is a separate conversation entirely. Anyone hoping for a fixed reopening date should watch for the Corps' November report rather than expecting resolution this fall. Sunset walks, fishing spots, and the paved walkway there remain in limbo until that funding question gets answered.

Two projects, two clocks, one beach. Knowing which repair you're looking at is the difference between checking back next week and checking back next year.