Drive the stretch of South Tamiami Trail near Beneva Road often enough and you've probably clocked the signage promoting "SSQ" and a 2026 arrival. That promise is now a year old. Meanwhile, a few miles north on the Legacy Trail, a project that got far less fanfare finished exactly when officials said it would. If you live near Palmer Ranch and have been tracking either one by the calendar rather than the renderings, here's where things actually stand.
On March 31, 2026, Sarasota County cut the ribbon on a new stretch of the Legacy Trail near the Pompano Trailhead, just south of the county fairgrounds. The project added a six-foot-wide paved pedestrian path running parallel to the main trail for 1.5 miles, giving walkers and joggers their own lane separate from cyclists, scooters and e-bikes. County commissioners had approved the wider corridor back in 2023, targeting the busiest sections of the trail between downtown Sarasota and the Palmer Ranch area, and this spring's opening was the first completed phase of that plan.
The number that makes the project worth noticing is usage. Sarasota County estimates the Legacy Trail draws more than 600,000 users a year, and anyone who has tried to walk a dog on it during peak hours already knows what that volume feels like when bikes, joggers and strollers share one lane. The 1.5-mile phase cost just over $900,000, funded through a mix of a Florida Department of Environmental Protection trails grant and matching support from the Friends of the Legacy Trail and the Sarasota-Manatee Bicycle Club. It's part of a larger 4.18-mile widening effort financed through a combination of state grants, grant-matching funds, impact fee revenue and private donations totaling roughly $1.3 million across every phase. Two more phases are planned, though the county hasn't attached dates to them yet.
For context on why this particular stretch matters to Palmer Ranch specifically: the Legacy Trail's original 2008 route ran ten miles north from the Venice Train Depot into Palmer Ranch, which is where the trail terminated for years before the downtown extension was built. Residents who ride or walk north from Palmer Ranch toward downtown are exactly the users this widened section was designed for. That part of the plan is finished, in use, and matched the timeline the county gave.
The former Sarasota Square Mall tells a different story so far. The mall opened in 1977 and closed in 2024 after years of decline, and demolition began in early 2025 to make way for a mixed-use redevelopment on the nearly 100-acre site at the corner of US-41 and Beneva Road. By August 2025, signage on the property was already promoting "SSQ" as coming in 2026, and Metro Commercial's Rod Castan, who is handling leasing for developer Torburn Partners, said in a public post that the first phase would be delivered that year.
A year later, that specific claim hasn't held up in a way anyone can point to on a calendar. As of Torburn's most recent public update in May 2026, the retail phase was 88% pre-leased and construction was visibly underway, but no individual tenant, including Whole Foods, has announced a firm opening date. Palmer Ranch's own Master Association describes the community as covering roughly 60 square miles between I-75 and the Tamiami Trail, which puts this corner right at the community's edge. That proximity is exactly why the site has always functioned as the neighborhood's closest big-box retail cluster even though the mall property itself sits just outside Palmer Ranch's formal line.
What is confirmed, according to reporting from REBusinessOnline, is the tenant roster for Phase 1:
That's a real list of committed businesses, not a rendering. What's missing is the piece that actually changes your Tuesday errands: a date.
The residential half of the project shows the clock moving even more plainly. Back in November 2025, REBusinessOnline reported that the multifamily component was expected to break ground in the first quarter of 2026. That didn't happen. By May 2026, the Business Observer was reporting groundbreaking was now expected "this summer," a season later than originally stated. Construction financing for the 355-unit Sarasota Square Apartments, a project from Woodfield Development, didn't actually close until June 2026, when PNC Bank provided the loan. Woodfield had already paid Torburn Partners $18.2 million in March for the 4.5-acre parcel, but paying for land and securing a construction loan are two different milestones, and the gap between them stretched several months longer than the original public timeline suggested.
With financing now in place, groundbreaking was described as imminent as of late June, and the current projection has the first residents moving into the five- and six-story buildings in the first quarter of 2028, with full completion by the fourth quarter of that year. That's a specific, sourced date. It's also a useful reminder that "coming in 2026" and "residents moving in" are not the same claim, even when they describe the same address.
If your routine already routes you past that corner, nothing changes for you this year beyond more visible construction. The existing Costco and other long-standing tenants on the property are unaffected. Whole Foods shoppers in the area are still making the drive north to the University Town Center location for now, and that's likely to remain true through the rest of 2026 based on everything currently public.
What has changed, and what you can use today, is the trail. If you've been avoiding the Legacy Trail near the Pompano Trailhead because of the crowding, the new pedestrian lane is open now, not eventually.
The longer-term picture is still worth watching. Once Sarasota Square's Phase 1 opens, and once its planned 1,200 residential units and 530,000 square feet of retail and dining space are built out over the next several years, that corner will look and function differently than it does today. Palmer Ranch residents who've watched this site sit half-demolished for over a year have earned some skepticism about exact dates, and the record so far supports that skepticism. The trail delivered on schedule. The mall corner is still working toward its own sign.
Staying current on which local projects are real and which are still projections is part of what we do every day at First Light Real Estate. If you have questions about how any of this affects a specific street or community in Palmer Ranch, Let's Talk.